Annex 2 - Oxfordshire Rail Corridor Study

GRIP 1 order of magnitude cost ranges:  

 

 

Wolvercot North Jn to Appleford

 

Intervention

 Description

 Cost Range (£m)

Intervention 0

Wolvercot North Junction capacity increase

36.6

48.6

Intervention 1-5

Conversion of an Oxford station bay platform into a through platform and 4-tracking Oxford to north of Radley

508.2

675.3

Intervention 6

Independent Line from Oxford North Junction towards Oxford station

106.9

142.1

Intervention 7

Shorter Cut-Off connection from Oxford North Junction towards Oxford

22.2

29.5

  Intervention 8

Optional cross over on the Bletchley lines (discounted as unfeasible)

 

Total

 

673.9

895.5

 

 

Didcot to Highworth Junction

 

Intervention

 Description

 Cost Range (£m)

Intervention 9

Central loop line at Didcot North Junction

67.3

89.4

Intervention 10

New station at Grove*

107

134

Intervention 11

4-tracking eastwards from Wantage Road

229.8

304.3

Intervention 12

New crossovers at Wantage Road

  Intervention 13

Recovery of maintenance crossovers (removed from scope as required for maintenance and during disruption)

Intervention 14-16 and 18

Didcot area capacity enhancements, including Didcot Parkway platform 6

139.3

185.1

Intervention 15

Didcot Parkway platform 6 (individual cost)

42.2

55.9

Intervention 17

 Grade separation at Didcot East

988.3

1313.2

 

Total

 

1573.9

2081.9

 

*based on provision of category E station including buildings, interchange, parking and associated facilities.  The cost range for a basic platform only station with footbridge is £19m-£25m

 

Total Cost of all Interventions – £2,247.8m to £2,977.4m